Identified Milestone Month to be delivered Description
Month 1 September 2006 Project kick-off (All WPs)
Month 2 October 2006 Board meeting: project kick-off (All WPs) : Initial planning for coordination of data centres and partners to define a common European DCA strategy, definition of the preliminary project plan (D2), also for WP 3-6
Month 3 November 2006 First report to EU (under WP1 responsibility)
Month 7 March 2007 Functioning project web site (D1, under WP1 responsibility) : A major milestone providing one main tool for dissemination of knowledge about EuroVO-DCA and international visibility of the project
Month 8 April 2007 PCT meeting (All WPs) : Assessment of the first six months activity, updated program for the next six months
Month 9 May 2007 Second report to EU (under WP1 responsibility)
Month 12 August 2007 First EuroVO-DCA Workshop (D6, under WP3 responsibility)
Month 14 October 2007 PCT meeting (All WPs) : Assessment of Cycle 1 activity, draft Cycle 2 program in preparation of the Board meeting
Month 14 October 2007 Mid-term Board meeting (All WPs) : Assessment of Cycle 1 activities and revised project plan for Cycle 2 (D3), also for WP3-6
Month 14 October 2007 First periodic report to EU (D15, under WP1 responsibility)
Month 17 January 2008 EuroVO Computational Grid Workshop (D12, under WP5 responsibility)
Month 17 January 2008 EuroVO Theory Workshop (D10, under WP4 responsibility)
Month 20 April 2008 PCT meeting (All WPs) : Assessment of activity of the first six months of Cycle 2, updated program for the next six months
Month 24 August 2008 Second EuroVO-DCA Workshop (D7, under WP3 responsibility)
Month 26 October 2008 PCT meeting (All WPs) : In preparation of the final Board meeting, assessment of WP3-6 activities
Month 28 December 2008 Final Board meeting (All WPs) : Final assessment of the project work (also for WP 3-6), Medium term strategic plan for EuroVO-DCA (D4), Census of European data centres (D5)
Month 28 December 2008 Final report to EU (D16, under WP1 responsibility)

-- MathiasDepretz - 08 Nov 2006

Edit | Attach | Watch | Print version | History: r4 < r3 < r2 < r1 | Backlinks | Raw View | Raw edit | More topic actions...
Topic revision: r1 - 08 Nov 2006 - MathiasDepretz
 
This site is powered by the TWiki collaboration platform Powered by Perl This site is powered by the TWiki collaboration platformCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback